Update! Pictures were taken last week (April 19).

Pool’s very near completion. At the moment we’re just waiting for the lights and the pump to be installed.

New structure being put up on the opposite end of the lot, this will house the compressor and tanks.

Divers’ area. Tiled and waiting for poured concrete for the outside areas.

Completed dining area (except for a couple of tiles waiting for electrical outlets)



Another room being built to house the dive equipment. Notice also the bar under construction.

We’ve been delayed another week because the glass couldn’t arrive on time. Moved again to next week. Furniture’s already ready and we’ve had to delay delivery because of this. The kitchen’s also coming along nicely, will be meeting with the supplier today to discuss the final proposal, hopefully by next week we’d also be able to start with the kitchen. 2 weeks!